Upland Parcels (Lot 1, Lot 2 and uplands portion of Lot 3)
September 8, 2021 Update
Lot 3 Subarea Focused Soil Excavations have begun. Work associated with the focused soil excavations in the Lot 3 subarea began September 7, 2021. The work will be conducted in accordance with the 100% Remedial Design Details Report for the Focused Soil Excavations in the Lot 3 Subarea which was approved by the DTSC on August 24, 2020. The activities associated with the focused soil excavations in the Lot 3 Subarea are expected to continue through October 2021. The Lot 3 Subarea Excavation work is identified as one component of the DTSC-approved remedy identified in the Final Feasibility Study/Remedial Action Plan for the uplands portion of the property. Other remedial components of the approved remedy will be addressed in other design plans currently under review by the DTSC.